Mishra presented a concise overview of all of FNAL activities for the ILC. During the presentation some additional comments/questions were made:

  • SM noted that FNAL has positions available for Main Linac activities (the focus of FNAL work)
  • The clean-room string assembly infrastructure should be commissioned and ready for use by April this year. The first assembly planned is the 3.9GHz cavities for TTF (summer).
  • FNAL are expecting to be ready for the DESY ‘cryomodule kit’ by the Fall.
  • Cryomodule 2 will be a TTF type 3+ constructed from the current cavities available. These cavities are the current long TTF-type and are not suitable for the planned ILC-type CM (CM 3). The cold-mass and cryostat will be ordered from Zanon. SM pointed out that there is a time slot available in the schedule to do this, and will gain them additional string-assembly / system performance experience before construction of CM3 [response to question].
  • SM commented at the end of his presentation that there was a need for ‘good information exchange’ at the Bangalore workshop, and stressed the need for working sessions. He also noted that 75 people had registered for the GDE meeting

--------------------------------------------------------------------

EC Closed Session

Approve last weeks "Public EC Meeting Summary"

The public minutes from 9/2 were approved.

Announcements

There were no announcements

Action Items

  • Agenda for Bangalore (5-Jan-06)- (Fumi, Tor)
    Parallel working sessions have now been included due to requests from specific groups. The agenda will now be posted
  • Vancouver Meeting Report (5-Jan-06)- (Gerry)
    The local organizers need additional input on what is needed for the program The Vancouver will be our major GDE meeting and need to do a good job on the organization.

Valencia Meeting Information and GDE Contact

BF will act as GDE liaison to the Valencia organising committee. It was noted that the current proposal looked like a 3.5 day workshop and we might need more.